The Starbucks project is located at 864 Folly Road, Charleston, SC 29412.

Project Manager: Gene Garrett | Superintendent: Mike Kucish 

Architect: Coast Architects, Inc.

Owner: FEWG 2, LLC

Project Overview:

The project consists of the construction of a new two story, 14,995 SF office building and site. 

 

June Progress 

June Schedule 
Roof trust framing Complete wall sheathing
Roof sheathing Set roof curbs
Roof blocking Architectural wall panels at mockup
Wall framing inspection passed Parapet sheathing 
Wall sheathing started   Exhaust Fan and Rail Roof Curbs
Window glass ordered Scaffolding for exterior  
Awning steel complete Roofing insulation/membrane  
Framing Inspection Passed Exterior sheathing complete 
Exterior Wall and Parapet wall sheathing Complete mock up for inspection 
Roof Sheathing   
Set RTU curbs at roof  

May Progress 

End of May Schedule 
Mock up wall flashing, insulation and brick ties Erect steel columns and beams
Exterior wall framing to truss bearing height with wall nailers Roof truss installation 
Steel fabrication offsite Wall nailers at steel beams
Site wall foundations poured each side of curb cut Site wall foundations and dumpster pad 

April

Goals for Next Month
Building Layout Complete Slab Formwork
Thickened Slab Excavations Complete Plumbing Rough in Slab/Inspections 
Formwork in Place Complete Electrical Rough in Slab/Inspections
Rebar Delivery Mock Up Steel Complete
Formwork in Progress at Slab Perimeter Mock Up Wall Framing
Site Storm Drainage/Roof Drains  
SCE&G located Electrical Service onsite