The St. Andrews project is located at 440 Whilden St, Mount Pleasant, SC 29464.

 

Project Overview 

  • The work consists of building addition and renovation of current church.
  • Architect: The Middleton Group
  • Owner: St. Andrew’s Church Mount Pleasant

 

November/December

  • Continuing to install concrete foundations; started concrete wall forming
  • Underground electrical conduit is installed
  • Underground plumbing ground work is installe
  • Concrete Saw cutting of slabs in the existing building is underway to prepare for new foundations
  • Water and Sprinkler lines that serve the existing facility are being relocated

 

Previous 

  • Providing services to re-establish fire alarm monitoring to the historic church and adjacent Sam’s Hall, due to the existing fire alarm panel was located in the fire building and is not able to be re-used.
  • Start asbestos abatement work at the Day School in preparation for the building to be demolished
  • Working with the design team on providing cost analysis for demolition of the fire building and re-build costs for the damaged worship building.