The Seacoast Worship Center Expansion is located at 750 Long Point Road, Mount Pleasant, SC 29464.

Project Manager: Gene Garrett | Superintendent: John Porter

Architect: LS3P

Owner: Seacoast Christian Community 

Project Overview:

The project consists of adding a new two story addition to the existing worship center. The new concrete tilt up construction addition will house a new lobby, 2,400 fixed seat auditorium, green room spaces, production suite, new restrooms, mother's rooms, and other necessary support spaces to include demolition of portion of the existing building to make connection to the new construction. 

 

March Project Updates

Goals for Next Month

Complete tilt up wall panels  Scaffolding at the Sanctuary 
Complete roof decking sanctuary   Set HVAC curbs at the roof
Roof steel at low roof areas Light gauge roof framing for sloped roofs
Measure storefront and order glass  TPO roofing begin

Previous Project Updates

Set steel in the stairway
Set panels and trusses
Steel started 
Roof rails
Demo the stairs and the wall
Pour panels are 40% complete
Tilt wall on-going
Begin to remove existing stairs
Continue with decking 

Seacoast