The K. Hovnanian's Four Seasons at Lake of Cane Bay projects are located at 322 Cane Bay Boulevard, Summerville, SC.

 

Project Overview 

  • The project consists of the Gatehouse, Entrance Monuments, Clubhouse Sitework, and Pools.
  • Architect: Fieldstone Architecture & Engineering 
  • Owner: K. Hovnanian's Four Seasons at Lakes of Cane Bay, L.L.C.

 

November/December

  • Furniture begins to get assembled and moved into the clubhouse
  • The clubhouse celebrated their grand opening on December 14, 2018 for residents 
  • Sitework continues on the exterior 

 

May

  • Clubhouse: Exterior Siding is complete, wall and ceiling inspections are complete in A & B, Scaffolding is being erected in Natatorium, Wall insulation to start next week, drywall to start soon.
  • Pool & Tennis Buildings: Building pads are tested, concrete crew to mobilize next week to start foundations.
  • Hardscapes/pool/dock: Dock pilings and tie backs are installed, site grading for hardscape has started, roof drain leaders are tied in, water is  turned on. Pool construction to resume early June

 

April (Cont.)

  • Week of 4/16
  • Exterior pool piping is being tested, kiddie pool is being excavated
  • Waiting on drawing updates for A drawings, on-going change order coordination with the owner
  • Owner provided notice to proceed on Pool Cabana & Tennis Buildings
  • Exterior siding and ISO is ongoing at Building C
  • Week of 4/30
  • Exterior siding to be completed this week at Natatorium.
  • Interior rough-in of electrical and mechanical trades on-going.
  • Fire Sprinkler piping was delivered and rough-in has started.
  • Layout of Pool Cabana/Tennis building to be completed. Building pads to be done this week.
  • Site conduit install on-going.
  • Materials for dock bulkhead were delivered.

 

April 

  • Week of 4/23
  • Exterior siding to be completed this week.
  • Interior rough-in of electrical and mechanical trades on-going.
  • Fire protection system installation to start this week.
  • Exterior pool piping was passed and backfilled, kiddie pool work to resume in early May.
  • Water meters have been set, site water is in service.
  • Drawing revisions received.
  • Layout of Pool Cabana/Tennis building to be completed.
  • Site conduit install on-going.

 

March

  • Exterior siding is ongoing at Building C
  • Interior rough-in of electrical and mechanical trades on-going
  • Exterior pool piping rough-in is on-going
  • Waiting on drawing updates to proceed with ordering materials
  • Storm water revisions were completed
  • ISO insulation on walls to start week of 4/2 at Natatorium

 

January/February 

  • Storm revisions are on-going
  • Siding is continuing on exterior
  • Exterior siding and trim has started
  • MEP rough-in is on-going throughout the building
  • Outdoor pool construction is underway