The East Bridge Town Lofts Exterior Repairs project is located at 269 Alexandra Drive, Mount Pleasant, SC 29464.

Architect: Glick/Boehm & Associates, Inc.

Owner: East Bridge Town Lofts HOA

Project Overview:

The project consists of the exterior repairs of East Bridge Town Lofts. Work includes but isn't limited to replacement of roofs, exterior cladding, porches, stairs, railings, window & door replacement.

June Project Updates:

Building 277

All items complete except exterior handrails. Mock up was approved. Rails are in fabrication.

Exterior sidewalk work to start (owner is handling directly)

Building 273

Heat Strip replacement is 50% complete at HVAC units.

Exterior handrails are being fabricated.

Building 275

Fascia and soffit revisions to four locations are underway.

Siding and Paint will be completed next week. (95% complete) Exterior Handrails are being fabricated

Building 278

Fascia and soffit revisions to four locations are underway.

Siding and Paint will be completed next week. (60% complete) Exterior Handrails are being fabricated Attic firewall work is complete

Building 276

Siding is 85% complete

Roofing is complete

Sunrooms are 50% complete

Electrical 100% complete

Attic firewall work is complete

Building 271

Framing is 75% complete

Roofing is 50% complete

Window replacement is 100% complete

Sunrooms are 15% Complete

Building 272

Demolition of stairs/porches is 95% complete Concrete foundations and slabs are 75% complete

Next Building 274 (to start week of 7/9/18)

 

May Project Updates:

Week of 5/20

Building 272: Demolition has started, 40% complete

Building 271: Concrete is 100% Complete, framing has started

Building 276: Framing complete, inspections for electrical and framing are scheduled

Building 278: Siding is 95% complete, sunroom finishes underway, paint prep to start

Building 275: Siding is 98% complete, painting is 30% complete

Building 273: Fire wall repairs are complete in attic. Waiting on handrail installation.

Building 277: Fire wall repairs are complete in attic. Waiting on handrail installation.

 

 

Week of 4/30

Building 277 – Punch out Exterior 277, waiting on handrails.

Building 273 – Final punch on interior repairs, skirting complete on stairs, waiting on handrails

Building 275 – Siding to resume this week (owner delay). Reframed stairs that were deficient.

Building 278 – siding work on-going. Roof Completed

Building 276 –framing, sheathing and window replacement on-going. Electrical upgrade work in progress.

Building 271 – Foundations on-going, all stair towers are demolished

 

April Project Updates:

Building 277 – Smoke detector installation complete. Railings on order.

Building 273 – Complete all interior punch items week of 4/23. Smoke detectors are complete. 

Building 275 – Siding to resume week of 4/23, reframing of Stairs at unit 11/12.  Smoke detectors are installed.

Building 278 – siding work on-going, smoke detectors and electrical work complete

Building 276 –framing, sheathing and window replacement on-going. Electrical upgrade work in progress.

Building 271 – Foundations on-going, demolition of two stair towers to take place week of 4/23.

 

March Project Updates:

Building 277 - painting to be completed the week of 3/19

Building 273 - painting has started, siding is now complete

Building 275 - framing inspection to be completed this week, siding to start, electrical upgrade work is complete

Building 278 - framing is nearly complete, electrical upgrade work is resuming, to be completed week of 4/2

Building 279 - demolition is complete, foundation work to wrap up week of 3/19

Building 277 - installation of smoke detectors week of 3/26

Building 273 - Continue painting exterior, complete GWB work in sunrooms week of 3/26

Building 275 - Framing inspection completed, siding is on-going, duct repairs to be completed in attic week of 3/26

Building 278 - Framing will be completed the week of 3/26, electrical work on-going, roofing has started

Building 276 - Foundation work to be completed the week of 3/26, siding removal and sheathing replacement to start

Building 271 - Demolition on front side of building started

 

Previous Project Updates:

Siding is nearing completion on Building 277

Demolition has started on Building 276

Framing of stair towers and porches is underway at Building 278

Roof has been installed on Building 275